Josh | July 2, 2012 | 0 Comments
The large sandstone terrace is now grouted and ready for sealing from the elements.
The cast stone ballastrade arrives next week, our teams will be forming this during weeks 6 & 7 leaving the planting scheme and lighting system to be completed in week 8.
The design team are hard at work on the planting scheme for this vast north facing aspect, like the colour of the sandstone the scheme is being designed to brighten what was a dull tired terrace into a vibrant, colourful space that our client’s will be enticed to spend their time in.
We can’t wait for this one to come together….