Stuart | January 31, 2013 | 0 Comments
This project is now into day 4.
The site team have excavated the area to formation level, installed all the drainage channels and underground cables, today they are installing the 1st entrance balmouth edgings and rumble strip using 100mm x 100mm x 200mm Naturally cropped granite kerbs.
The schedule is to install the Brick edging and remaining Sett edging over the next 2 days, then we should be able to install the porous asphalt base layer.
Its sunny today, so good progress is expected, Heavy rain though tomorrow!!